A2 Media Production


Week
Date
Activity
-3
28th Nov
Pitch practise week. Complete planning. Complete pitch.
-2
5th Dec
Pitch Week: pitch practise week. Complete planning.
-1
12th Dec
Pitch Week: Planning deadline.
Xmas hols
19th Dec

Xmas hols
26th Dec

1
2nd Jan
Production

2
9th Jan
This week I plan to complete several things, find people willing to be models for photo shoot, booking my photo shoot in the atrium, think of ideas for models, costume makeup etc. I plan to search for several hair an makeup ideas which I think would be good ideas to use on my model for the photo shoot on google images and save the pictures which I want to imitate.

3
16th Jan
Finish my flat plans adding detail and some colour to them.  

4
23rd Jan
Complete my contingency plans and scan my flat plans of the front cover of my magazine and two of my double page spreads and upload them to my blog. 

5
30th  Jan
Make sure I have someone who can definitely be the model for my photo shoot. Look for suitable outfits and makeup for the model on the day of the photo sheet and complete my article planning sheet.
6
6th Feb
This week I will be doing my photo shoot, my photo shoot is booked for Monday (today). I will need to prepare everything I need all of my clothes, makeup, models ready and also make sure that I also have backups, for example extra clothes, make-up and even another model. While I wait for the photo shoot room I plan to work on both of my double page spreads for my magazine.

After I finish my photo shoot I will see if any of the images produced are not satisfactory and think about how I could change and improve them.

Half term

13th Feb

Look through all of the photos I have produced, analyse them and think about which I think are the best images and will be suitable for my magazine.
7
20th Feb

Make finishing touches to both of double page spreads and also work on front cover of mag.
Choose photo I want to use for my front cover, check to see if I can improve the image quality in any way.

8
27th Feb
Peer & Assessor review
9
5th March

Evaluation E

10
12th March
Evaluation D

11
19th March
Evaluation C
12
26th March
Evaluation B

Easter
2nd April


Easter
9th April


13
16th April
Unit 6 Evaluation deadline